# Understanding annualised working time

Annualisation spreads working time over a reference period rather than week by week: some weeks are high, others low, and what counts is the total for the period. This article introduces the Annualised working time module, its screens and its key concepts, for HR, managers and the employees concerned.

## Before you start

- The **Annualised working time** module is installed from the application store (see [Installing modules and choosing who can use them](https://illizeo.com/en/centre-aide/settings-installing-modules/)). It relies on the **Attendance Management** module, which must also be installed: only approved time entries count. **Scheduling** is optional.
- The **Annualised working time module — Access** permission (role matrix, Annualisation module, Access level) opens the module. Every standard role holds it by default, including **All employees**.
- An employee only has a counter once their contract is assigned to a scheme (see [Assigning contracts and managing periods](https://illizeo.com/en/centre-aide/annualisation-assignments-periods/)). The other permissions are described in [Administering the annualised working time module](https://illizeo.com/en/centre-aide/annualisation-administer/).

## Where to find the module

The **Annualised working time** menu has two entries: **Annualised working time › Home**, the module’s home page, and **Annualised working time › Settings**, which opens the schemes and is only shown to those who can read them (the administrator, by default). The home page is organised in views; each one only appears if you have the right to it:

| View | What it shows | Who sees it, by default |
| --- | --- | --- |
| My counter | Your own counter. | Any employee with an assigned contract |
| My team | The current counters within your scope. | Administrator, HR Manager, Manager, Auditor |
| Dashboard | One line per sub-company: employees tracked, drift, reviews to close. | Administrator, HR Manager, Auditor |
| Reviews and closings | End-of-period reviews and their closing. | Administrator, HR Manager, Auditor |
| Alerts | Open control alerts. | Administrator, HR Manager, Manager, Auditor |
| Exceptional hours | Declared exceptional hours. | Administrator, HR Manager, Manager, Auditor |

With no view at all, the home page shows “No counter yet: employees will appear here once an annualisation scheme is assigned to their contract.”. If you can read the schemes, the **Set up the schemes** button leads to them.

![Annualised working time home page with the My counter, My team, Dashboard, Reviews and closings, Alerts and Exceptional hours views](https://i0.wp.com/illizeo.com/wp-content/uploads/2026/11/annualisation-comprendre-01.en_.png?resize=800%2C348&quality=80&ssl=1)
The module’s home page, organised in views according to your rights

The settings are grouped under **Settings › Annualised working time**: **Annualisation schemes**, **Assignments and periods**, **Controls**, **Working time records**, **Carry-over from another tool** and **Full export (reversibility)**. Each tile only appears to those with the right to it: an HR Manager finds the assignments and the carry-over there, the administrator finds every tile.

![Annualised working time settings with the Schemes, Assignments and periods, Controls, Working time records, Carry-over and Full export tiles](https://i0.wp.com/illizeo.com/wp-content/uploads/2026/11/annualisation-comprendre-02.en_.png?resize=800%2C314&quality=80&ssl=1)
The module’s settings, under Settings

Every screen of the module has a **Help** button: it opens a panel on the right explaining what you do on the screen, what you need to know and the permissions required. Next to the button, each concept used on the screen shows its definition in one click.

![Help panel of the My counter view with its What you do here, Good to know and Rights sections](https://i0.wp.com/illizeo.com/wp-content/uploads/2026/11/annualisation-comprendre-03.en_.png?resize=448%2C476&quality=80&ssl=1)
The Help button explains each screen

## Key concepts

### Reference period

The period over which working time is counted: a year, a season or a duration set in the scheme. The counter and the review cover it. Its start is set in the scheme:

- **Fixed date**: a day and a month, for example 1 January;
- **Employee’s own date**: a date set on the assignment, by default the contract start date;
- **First week of a month**: the **First full week** of the chosen month, or the **First week, even overlapping**;
- **Contract duration**: reserved for the seasonal scheme, whose period is the contract.

Apart from seasonal schemes, the length is counted in weeks: 52 by default, 104 at most. Joining, leaving, a change of scheme or the end of the assignment during a period shortens the employee’s period.

### Target

The volume to be worked over the period: hours of actual work, or days worked for an annual day rate. It is entered in the scheme, then calculated for each employee in proportion to their weeks of presence in the period and, if the scheme says so, to their activity rate. For a seasonal worker, the target is the reference weekly hours multiplied by their weeks of contract.

### Counter

The counter follows the current period, week by week:

| Counter line | What it contains |
| --- | --- |
| Target | The target for the employee’s period. |
| Target to date | The share of the target matching the days already elapsed, according to the theoretical schedule. |
| Approved worked time | Time entries approved in attendance. |
| Credited absences | Approved absences, credited according to the scheme’s rule. |
| Awaiting approval | Hours clocked but not yet approved: shown separately, outside the variance. |
| Remaining planned | What is still planned until the end of the period. |
| Projected at period end | Worked time and absences, plus the remaining planned time. |
| Variance to date | Worked time and credited absences compared with the target to date. |
| Projected variance | The projection compared with the period target. |

### Variances and projection

A positive variance to date means the employee is ahead of what they should have done by today; a negative one means they are behind. The projection tells you what the counter will reach at the end of the period if nothing changes: for the days ahead, the module reads the published shifts if Scheduling is open to the employee, otherwise the theoretical schedule of their attendance profile, public holidays off included.

## Scheme types

| Type | Principle |
| --- | --- |
| Modulated annualisation | A target in hours over the period, a weekly range, overtime counted weekly and at the end of the period. |
| Seasonal (period = contract) | The period is the contract; successive contracts form separate periods or a single period. |
| Modulated part-time | Part-time work whose duration varies from week to week within bounds; beyond the target, additional hours at the end of the period. |
| Annual day rate | A scheme counted in days worked, with a cap that day buy-backs raise. |

The type is chosen when the scheme is created and cannot be changed afterwards. See [Creating and updating an annualisation scheme](https://illizeo.com/en/centre-aide/annualisation-schemes/) and [Annual day rate and modulated part-time](https://illizeo.com/en/centre-aide/annualisation-day-rate-part-time/).

## What the module does and does not do

- **Hours and days, never an amount.** The module produces quantities (hours, days, and the premium rates that label them) sent to payroll. It calculates no pay: valuing them is your payroll software’s job.
- **No legal value imposed.** Target, thresholds, quota and premiums are the ones you enter in the scheme, or that an installed pack proposes. The module serves every country.
- **Public holidays.** The annual target you enter is deemed to account for them: a public holiday does not change it. For a seasonal worker, each public holiday falling on a working day removes that day’s theoretical hours from the target.
- **The employee’s day.** The counter works in the employee’s time zone: before that day it reads worked time; from that day on, planned time.
- **Updates.** An approved time entry, an approved absence or a published shift has the week concerned recalculated, in the background; every night, all open periods are recalculated. A closed period no longer is.

## Good to know

- On the days a contract is assigned, annualisation counts overtime and sends it to payroll: the attendance profile neither counts, pays nor flags it. If that profile also sets an annual target, the hour counters tab says so: “The annual target is carried by the annualisation scheme of the contract: it is the reference.” (see [Hour counters](https://illizeo.com/en/centre-aide/attendance-hour-counters/)).
- If the employee’s attendance profile keeps a time account, the list of assignments shows it with the **Time account** mention: both counters coexist.
- Without Scheduling, the module’s home page reminds you: “Without Scheduling, the end-of-period projection will read the theoretical hours of the attendance profiles.”.

## FAQ

### Why are this week’s hours missing from my worked time?

Only approved time entries count. Hours awaiting approval appear on the **Awaiting approval** line and join worked time as soon as they are approved.

### I cannot see the My counter view.

It only exists if one of your contracts is assigned to an annualisation scheme. Contact your HR department.